Plants and Plant Products
Denial and Risk Assessment Determination
If a commodity is not approved, then the permit is denied. This
process should normally take less than two months.That denial is
not necessarily the end of the story. Governments and companies
can request a change in or a reassessment of the present status
of a prohibited commodity. This request generates a process by
which the PPQ Scientific Group determines if a risk assessment
is warranted.
If a risk assessment has not been done within the past 10 years,
then the Permit Unit may request that an assessment be conducted.
If a risk assessment has been conducted within the past 10 years,
then the Permit Unit will determine if conditions exist that
warrant reassessment. If the answer is yes, it will request a
reassessment. If the answer is no, then the Permit Unit will
continue to deny entry.
|